Environment Agency – Construction Permits Consultation

The Environment Agency has two construction permits for Sizewell C open for consultation:

Construction water discharge activity permit: The company needs to remove water from its construction site. This effluent includes rainfall running off the construction site and groundwater from excavations. The company is proposing 9 construction water discharge activities (WDAs) of trade effluent through 9 different discharge points. The receiving environments (Sizewell Foreshore, the North Sea, the Leiston Beck and surrounding tributaries) for each activity are provided in the application.

For more information regarding the construction water discharge activity permit, please visit: IP16 4UR, Sizewell C Limited, EPR/RP3820SH/A001: environmental permit consultation – Environment Agency – Citizen Space (environment-agency.gov.uk)

Combustion activity permit: The company also needs to operate static and mobile diesel generators at the construction site. The generators provide electricity to power tools and equipment needed for the construction of the power station. Mobile generators can be moved to different locations within the boundary of the permitted site, as required by the workforce.

For more information regarding the combustion activity permit, please visit: IP16 4UR, Sizewell C Limited, EPR/GP3226SQ/A001: environmental permit consultation – Environment Agency – Citizen Space (environment-agency.gov.uk)