Wide & Abnormal Load movements w/c 3 February

AIL movements in relation to the Sizewell C Project.

Updated 5 February

On Tuesday 4 February, there are four wide load movements planned.

The first two loads will be delivering a bulldozer and plant machinery to the to the Main Development Site. These loads are expected to arrive at 11:00 am. These will be police escorted.

The next two loads will be delivering excavator to the Main Development Site. These loads are expected to arrive at 12:00 noon. These will be police escorted.

These loads will follow the designated route to and from site- A12, B1122 East and Lovers Lane.

On Wednesday 5 February, there are four wide load movements planned.

These loads will be the delivery of office cabins to the Temporary Construction Site. These are expected arrive at 10:00 am and 11:00am and will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Thursday 6 February, there are thirteen wide load movements planned.

There are nine movements transferring cabins between the Ancillary Construction Area to the Temporary Construction Area. These loads will move in batches of two at 09:00am, 11:00 am 13:00 pm, 14:00 pm and 15:00 pm. These will be police escorted and will travel down Lovers Lane.

The remaining loads will be traveling to the Temporary Construction Area delivering plant machinery and articulated dump trucks. These loads will follow the designated route to and from site- A12, B1122 East and Lovers Lane and are expected to arrive at 10:0am, 13:00 pm and 14:00 pm and will be police escorted.