Wide & Abnormal Load movements w/c 15 September 2025

By SZC Community Relations | Published on 12th September 2025

AIL movements in relation to the Sizewell C Project

Updated 18 September 2025

On Tuesday 16 September, there are four wide load movement currently planned:

At 10:00, an excavator will be delivered to the Main Construction Area.

At 12:00, two deliveries of steel tubes will be made to the Main Construction Area.

At 15:00, a delivery of steel tubes will be made to the Main Construction Area.

On Wednesday 17 September, there is nine wide load movement currently planned:

At 09:00, plant machinery will be removed from the Main Construction Area and two modular buildings will be delivered to the Main Construction Area.

At 11:00, two modular buildings will be delivered to the Main Construction Area.

At 13:00, two modular buildings will be delivered to the Main Construction Area.

At 15:00, a crane will be removed from the Main Construction Area and two modular buildings will be delivered to the Main Construction Area.

On Thursday 18 September, there is one wide load movement currently planned:

At 14:00, an excavator will be removed from the Buckleswood Road railway compound.

On Friday 19 September, there are six wide load movement currently planned:

At 09:00am, two modular buildings will be delivered to the Main Construction Area.

At 11:00am, two modular buildings will be delivered to the Main Construction Area.

At 13:00am, one modular building will be delivered to the Main Construction Area

At 15:00, a crane will be delivered to the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.

 