Wide & Abnormal Load movements w/c 27 April

By SZC Community Relations | Published on 24th April 2026

AIL movements in relation to the Sizewell C Project

Destinations:

MCA - Main Construction Area

ACA - Ancillary Construction Area

TCA - Temporary Construction Area

GRR - Green Rail Route Compound

SLR - Sizewell Link Road

Arriving Load Description Gate Delivery/Collection Route
27/04/2026, 13:00 Storage Tanks TCA Delivery Designated route A12, B1122 & Lovers Lane
28/04/2026, 09:00 Welfare Unit TCA Collection Designated route A12, B1122 & Lovers Lane
28/04/2026, 09:00 Welfare Unit TCA Collection Designated route A12, B1122 & Lovers Lane
28/04/2026, 12:00 Steel MCA Delivery Designated route A12, B1122 & Lovers Lane
28/04/2026, 12:00 Welfare Unit TCA Collection Designated route A12, B1122 & Lovers Lane
29/04/2026, 09:00 Excavator TCA Collection Designated route A12, B1122 & Lovers Lane
29/04/2026, 09:00 Excavator TCA Collection Designated route A12, B1122 & Lovers Lane
30/04/2026, 10:00 Welfare Unit TCA Collection Designated route A12, B1122 & Lovers Lane
30/04/2026, 12:00 Steel MCA Delivery Designated route A12, B1122 & Lovers Lane