Wide & Abnormal Load movements w/c 31 August 2026

By SZC Community Relations | Published on 28th August 2026

AIL movements in relation to the Sizewell C Project

Destinations:

MCA - Main Construction Area

ACA - Ancillary Construction Area

TCA - Temporary Construction Area

GRR - Green Rail Route Compound

SLR - Sizewell Link Road

 

Start Date & Time Load Description Gate Delivery/Collection Route
01/09/2026 09:00 Crane TCA Delivery Route 1a A12 Seven Hills to TCA
01/09/2026 14:00 Concrete ring Plaza Roundabout Delivery Route 1a A12 Sevenhills to Plaza Roundabout
01/09/2026 14:00 Concrete ring Plaza Roundabout Delivery Route 1a A12 Sevenhills to Plaza Roundabout
01/09/2026 14:00 Excavator MCA Collection Route 1a A12 Seven Hills to MCA
01/09/2026 14:00 Excavator MCA Collection Route 1a A12 Seven Hills to MCA
02/09/2026 09:00 Articulated Dump Truck TCA Collection Route 1a A12 Seven Hills to TCA
02/09/2026 09:00 Articulated Dump Truck TCA Collection Route 1a A12 Seven Hills to TCA
02/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
02/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
02/09/2026 12:00 Ballast Weights MCA Delivery Route 1a A12 Seven Hills to MCA
02/09/2026 12:00 Piling Rig MCA Delivery Route 1a A12 Seven Hills to MCA
02/09/2026 13:00 Plant TCA Delivery Route 1a A12 Seven Hills to TCA
02/09/2026 13:00 Articulated Dump Truck TCA Delivery Route 1a A12 Seven Hills to TCA
03/09/2026 09:00 Articulated Dump Truck TCA DepartureOnly Route 1a A12 Seven Hills to TCA
03/09/2026 09:00 Articulated Dump Truck TCA DepartureOnly Route 1a A12 Seven Hills to TCA
03/09/2026 09:00 Excavator TCA DepartureOnly Route 1a TCA to A12 Seven Hills
03/09/2026 09:00 Excavator TCA DepartureOnly Route 1a TCA to A12 Seven Hills
03/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
03/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
04/09/2026 09:00 Articulated Dump Truck TCA DepartureOnly Route 1a A12 Seven Hills to TCA
04/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
04/09/2026 11:00 Precast concrete MCA Delivery Route 1a A12 Seven Hills to MCA
04/09/2026 12:00 Plant TCA Delivery Route 1a A12 Seven Hills to TCA