Destinations:
MCA/MDS - Main Construction Area
ACA - Ancillary Construction Area
TCA - Temporary Construction Area
GRR - Green Rail Route Compound
SLR - Sizewell Link Road
| Start Date & Time | Load Description | Gate | Delivery/Collection | Route |
| 30/11/2026 09:00 | Crane | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 09:00 | Ballast Vehicle | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 09:00 | Ballast Vehicle | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 12:00 | Piling Equipment | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 12:00 | Piling Equipment | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 15:00 | Piling Equipment | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 30/11/2026 15:00 | Piling Equipment | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 01/12/2026 11:00 | Storage Tank | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 01/12/2026 11:00 | Storage Tank | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 02/12/2026 10:00 | Bull Dozer | Green Rail Route Buckleswood | Collection | Designated RouteA12, B1122 & Lovers Lane |
| 02/12/2026 11:00 | Storage Tank | TCA | Delivery | Designated RouteA12, B1122 & Lovers Lane |
| 02/12/2026 13:00 | Bull Dozer | Green Rail Route Buckleswood | Collection | Designated RouteA12, B1122 & Lovers Lane |
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!