Leiston-cum-Sizewell

Land East of Eastlands Industrial Estate (LEEIE)

Activity: Site construction

Start date: 30th October 2023

End date: 31st December 2024

Sizewell C has acquired the land east of Eastlands Industrial Estate, off King George’s Avenue and Lovers Lane  (known locally as Big Field and Little Field), where we are constructing office accommodation, sidings for the Green Rail Route, and a caravan park.

A bell-mouth entrance from this Ancillary Construction Area (ACA) onto King George’s Avenue has been created and work is underway to complete the office facilities and parking for staff.

  • Please note: Work inside the modular office buildings is taking place on some Sundays during June 2024. These works do not involve an machinery and will be inside the buildings only. All work will be finished before 4pm.

All necessary works on the site will be carried out under supervision of an Ecological Clerk of Works, including surveys for nesting birds, bats and badgers, which will be carried out in accordance with protected species licence conditions where they apply.