Footpath closures
Benhall

Two Village Bypass

  • Activity: Footpath closures
  • Start Date: 7th September 2026
  • End Date: 7th February 2027

Temporary Closure of Public Right of Way: Benhall 29.

As part of the construction phase of Sizewell C nuclear power station, public footpath Benhall 29 will be closed to allow construction of the Two Village Bypass at Friday Street.    A diversion will be in place from the 7th September 2026 to the 7th February 2027 using the footpath Farnham 4.  This diversion will be sign posted on the ground.

This work was approved by the Sizewell C Development Consent Order (2022).