Theberton and Eastbridge, Wickham Market

Temporary Construction Area (TCA)

Activity: Traffic Management

Start date: 3rd February 2025

End date: 14th March 2025

UK Power Networks (UKPN) need to undertake diversionary works to their network on the southern part of Eastbridge Road.

In order to minimise disruption to the public, the works will be undertaken under a night-time road closure and the road will be open to traffic during the day.

We are still engaging with UKPN on their programme, but the works will be undertaken at some time during the period between 3 February – 14 March 2025. At the time of writing, it is expected that UKPN will undertake the diversionary works between 17 February and 1 March 2025.

During the night-time closure, access from the B1122 to Eastbridge will be made from Church Street and vehicles leaving Eastbridge to access the B1122 would do so via Onner’s Lane.