Hacheston, Wickham Market

Southern Park and Ride

Activity: Site construction

Start date: 8th July 2024

End date: 2nd September 2024

Site enabling works on the Southern Park and Ride have commenced and involve the following initial works to prepare the site:

  • Site Perimeter fencing works: to be completed by end of July 2024
  • Site enabling works: from mid-July until the end of August 2024