Activity: Wide Load
Start date: 31st May 2024
End date: 31st May 2024
Additional Movements updated 30 May 2024.
On Friday 31 May, there will be three wide load movements:
The first movement will be a delivery of an excavator to the Temporary Construction Area and is expected to arrive at 10:00 am. This will be police escorted.
The next two movements will be delivering bulldozers to the Temporary Construction Area. These are expected to arrive at 11:00 noon. These loads will be police escorted.
These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.