Leiston-cum-Sizewell, Middleton cum Fordley, Theberton and Eastbridge, Yoxford

Temporary Construction Area (TCA)

Activity: Wide Load

Start date: 31st May 2024

End date: 31st May 2024

AIL movements in relation to the Sizewell C Project.

Additional Movements updated 30 May 2024.

On Friday 31 May, there will be three wide load movements:

The first movement will be a delivery of an excavator to the Temporary Construction Area and is expected to arrive at 10:00 am. This will be police escorted.

The next two movements will be delivering bulldozers to the Temporary Construction Area. These are expected to arrive at 11:00 noon. These loads will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.