Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 8th March 2025
  • End Date: 14th February 2025

On Monday 10 March, there are nine wide load movements planned.

At 11:00 there will a delivery of two dumper truck and a crane to the Main Development Site followed by two modular buildings to the Temporary Construction Area.

At 11:00 there will a delivery of two modular buildings to the Temporary Construction Area.

At 12:00 there will a delivery of two modular buildings to the Temporary Construction Area.

At 14:00 there will be a delivery of two modular buildings to the Temporary Construction Area.

On Tuesday 11 March, there are four wide load movements planned.

At 09:00 there will a delivery of two cabins to the Temporary Construction Area.

At 10:00 there will a two deliveries of plant equipment to the Temporary Construction Area.

On Wednesday 12 March, there are eleven wide load movements planned.

At 10:00 there will be a delivery of two cabins to the Main Construction Site.

At 11:00 there will be two modular buildings and a crane being delivered to the Temporary Construction Area.

At 12:00 there will be two modular buildings being delivered to the Temporary Construction Area.

At 14:00 there will be two modular buildings and two dumper trucks being delivered to the Temporary Construction Area.

On Thursday 13 March, there are eleven wide load movements planned.

At 10:00 there will be two deliveries of building materials to the Temporary Construction Area.

At 11:00 there will be two modular buildings and a crane being delivered to the Temporary Construction Area.

At 12:00 there will be two modular buildings being delivered to the Temporary Construction Area.

At 14:00 there will be two modular buildings and two dumper trucks being delivered to the Temporary Construction Area. Followed by two deliveries of building materials to the Temporary Construction Area.

At 15:00 there will be a delivery of a dumper truck to the Main Construction Site.

On Friday 14 March, there are nine wide load movements planned.

At 11:00 there will be two modular buildings and a crane being delivered to the Temporary Construction Area.

At 12:00 there will be two modular buildings being delivered to the Temporary Construction Area.

At 14:00 there will be two modular buildings being delivered to the Temporary Construction Area.

At 15:00 there will be two deliveries of building materials to the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.