Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 18th October 2024

End date: 26th October 2024

On Friday 25 October, there are six wide load movements planned:

The first two loads are delivering articulated dump trucks to the Temporary Construction Area. These loads are expected to arrive at 10:00 am and will be police escorted.

The third load is delivering an excavator to the Temporary Construction Area. This load is expected to arrive at 11:00 am and will be police escorted.

The fourth load is delivering an articulated dump truck to the Green Rail Route compound on Buckleswood Road. This load is expected to arrive at 12:00 pm and will be police escorted.

The final two loads are delivering articulated dump trucks to the Green Rail Route compound on Buckleswood Road. These loads are expected to arrive at 15:00 pm and will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.