Main Development Site

Activity: Wide Load

Start date: 5th April 2024

End date: 20th April 2024

AIL movements in relation to the Sizewell C Project.

Week commencing 15 April 2024 we have the following wide and abnormal load movements making deliveries.

Monday 15 April: 1 Artic HGV will be delivering an excavator to the main construction site which is expected to arrive at 14:00. This will be police escorted.

Wednesday 17 April at approximately 11:00am there will be 2 x Low Loader HGV transporting articulated dump trucks to the Temporary Construction Area (TCA) adjacent to the main development site. These movements will be police escorted.

There will also be 2 further movements at approximately 13:00 pm on Wednesday 17 April, where 2 low loaders will be transferring two dumpers from the ACA to the TCA. These movements will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 east and Lovers Lane.