On Tuesday 17 December there are two wide load movements planned.
These loads will be the delivering articulated dump trucks to the Sizewell Link Road compound in Middleton Moor. These loads are expected to arrive at 10:00 am.
These load will follow the designated route to and from site – A12 and B1122 East.
On Wednesday 18 December there are two wide load movements planned.
These loads will be the delivering articulated dump trucks to the Sizewell Link Road compound in Middleton Moor. Thess loads are expected to arrive at 09:00 am.
These loads will follow the designated route to and from site – A12 and B1122 East.
On Thursday 20 December there are two wide load movements planned.
These loads are the removal of cranes from the Temporary Construction Area. These loads are expected to depart at 10:00 am.
These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.
RETURN TO SEARCHBe the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!