Activity: Wide Load
Start date: 14th June 2024
End date: 22nd June 2024
Week commencing 17 June 2024.
Updated 19 June 2024.
On Monday 17 June, there is one wide load movement, delivering a bulldozer to the Ancillary Construction Area. This load is expected to arrive at 11:00am. This will be police escorted.
These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane and King George Ave.
On Thursday 20 June, there are three wide load movements.
The first two will be delivering modular buildings to the Ancillary Construction Area. These load are expected to arrive at 11:00am. These will be police escorted.
These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane and King George Ave.
The third movement will be a delivery of an articulated dump truck to the Temporary Construction Site. This load are expected to arrive at 14:00 pm. This will be police escorted.
This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.