back
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 15th November 2024

End date: 23rd November 2024

Updated 19 November.

On Monday 18 November, there are seven wide load movements planned.

The first load is delivering an articulated dump truck to the Temporary Construction Area. This load is expected to arrive at 09:00 am.  This will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The second load is the removal of a chipper from the Main Development Site. This load is expected to depart at 10:00 am.  This will be police escorted.

This load will follow the designated route to and from site – Lovers Lane, B1122 West and A12.

The third load is delivering an articulated dump truck to the Temporary Construction Area. This load is expected to arrive at 12:00 pm.  This will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The fourth and fifth load is delivering excavators to the Trust Farm, Link Road Works. These loads are expected to arrive at 14:00 pm.  This will be police escorted.

These loads will follow the designated route to and from site – A12 and B1122 East.

The sixth and seventh load is delivering articulated dump trucks to the Trust Farm, Link Road Works. These loads are expected to arrive at 15:00 pm.  This will be police escorted.

These loads will follow the designated route to and from site – A12 and B1122 East.

On Tuesday 19 November there is one wide load movement planned.

This load is the collection of plant machinery from the Main Development site. This load is expected to depart from site at 12 noon. This will be police escorted.

This load will follow the designated route to and from site – Lovers Lane, B1122 West and A12.

On Wednesday 20 November there are three wide load movements planned.

These loads are the removal of cranes from the main development site and are expected to leave site at 10:00am and 12:00 noon.

These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.

On Thursday 21 November there are five wide load movements planned.

There will be four loads delivering welfare cabins to the Temporary Construction Area and are expected to arrive on site at 11:00am and 13:00 pm. These will be police escorted.

The fifth load will be delivering a articulated dump truck to Wild Aldhurst farm and will be police escorted and is expected to arrive at 13:00 pm.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Friday 22 November there will be three wide load planned.

The first will be a delivery of an articulated dump truck to our compound at Tinkerbrook Road for the two-village bypass. This is expected to arrive at 09:00 am. This will be police escorted

This load will follow the designated route to and from site using the A12.

The second will be a delivery of an excavator to the Temporary Construction Area. This is expected to arrive at 09:00 am and will be police escorted.

This load will follow the designated route to and from site using the A12, B1122 East and lovers Lane.

The third load will be a delivery of an articulated dump truck to Aldhurst Farm and is expected to arrive at 13:00 pm. This will be police escorted.

This load will follow the designated route to and from site using the A12, B1122 East and lovers Lane.