On Monday 19 May, there are four wide load movements planned.
At 09:00, an excavator will be leaving the Temporary Construction Area.
At 11:00, an excavator is being delivered to the Main Construction Site.
At 13:00, plant machinery is being delivered to the SLR compound in Middleton Moor and a dumper truck is being delivered to Aldhurst Farm on Lovers Lane.
At 13:00, two plant machines are being delivered to the Main Construction Site.
At 14:00, a delivery of a plant machinery to the Main Construction Site.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.
At 12:00, two modular buildings will be delivered to Leiston Airfield.
At 14:00, two modular buildings to Leiston Airfield and a crane is being delivered to the Main Construction Site.
On Wednesday 14 May, there are eleven wide load movements planned.
At 09:00, there is a delivery of two modular buildings to Leiston Airfield.
At 10:00, a dumper truck is being delivered to the Ancillary Construction Area.
At 11:00, a crane is being delivered to the Main Construction Site.
At 12:00, two modular buildings will be delivered to Leiston Airfield.
At 13:00, two plant machines are being delivered to the Main Construction Site.
At 14:00, two modular buildings to Leiston Airfield and a dumper truck is being delivered to Trust Farm.
On Friday 16 May, there are six wide load movements planned.
At 09:00, there is a delivery of two modular buildings to Leiston Airfield.
At 11:00, a crane is will be leaving the Main Construction Site.
At 12:00, two modular buildings will be delivered to Leiston Airfield.
At 13:00, two plant machines are being delivered to the Main Construction Site.
At 14:00, a delivery of a plant machinery to the Main Construction Site.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.
On Tuesday 20 May, there are eleven wide load movements planned.
At 09:00, a dumper truck will be leaving the Temporary Construction Area, and two modular buildings will be delivered to Leiston Airfield.
At 11:00, a delivery of sheet piles is being made to the Main Construction Site.
At 12:00, two modular buildings are being delivered to Leiston Airfield.
At 14:00, a modular building is being delivered to Leiston Airfield.
At 15:00, there will be four deliveries of sheet piles to the Main Construction Site.
On Wednesday 21 May, there are nine wide load movements planned.
At 09:00, two plant machinery are being removed from the Temporary Construction Area and taken away from site.
At 11:00, two deliveries of sheet piles are being made to the Main Construction Area and a delivery of a digger to the Accommodation Campus.
At 14:00, a delivery of plant machinery is being made to the Main Development Site.
At 15:00, two deliveries of sheet piles will arrive at the Main Development Site.
On Friday 23 May, there are seven wide load movements planned.
At 10:00, a delivery of materials is being made to the Main Development Site.
At 11:00, two delivery of sheet piles is being made to the Main Construction Site.
At 15:00, there will be three deliveries of sheet piles and one bulldozer to the Main Construction Site.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.
ane.
RETURN TO SEARCH
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!