Updated 5 December
On Monday 2 December there are two wide load movements planned.
The first load will be the delivery of a bulldozer to the Main Development Site. This load is expected to arrive at 11:00 am. This will be police escorted.
The second load is delivering an articulated dump truck to the Main Development Site. This load is expected to arrive at 14:00 pm. This will be police escorted.
These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.
On Tuesday 3 December there are six wide load movements planned.
The first two loads will be delivering materials to the Ancillary Construction Area. These loads are expected to arrive at 09:00 am. These will be police escorted.
The next four loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane
These loads are delivering welfare units Trust Farm Compound. These loads are expected to arrive at 12:00 noon and 14:00 pm. These will be police escorted.
These loads will follow the designated route to and from site – A12 and B1122 East.
On Wednesday 4 December there are four wide load movements planned.
These loads are delivering welfare units Trust Farm Compound. These loads are expected to arrive at 11:00 am and 13:00 pm. These will be police escorted.
These loads will follow the designated route to and from site – A12 and B1122 East.
On Thursday 5 December there is one wide load movements planned.
This load will be the delivery of digger to the Temporary Construction Area. This load is expected to arrive at 14:00 pm. This will be police escorted.
This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.
On Friday 6 December there are three wide load movements planned.
The first load will be the delivery a welfare unit to the Temporary Construction Area. This load is expected to arrive at 12:00 noon. This will be police escorted.
This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.
The next two loads are delivering units to the SLR compound in Middleton Moor. These loads are expected to arrive at 12:00 noon. These will be police escorted.
These loads will follow the designated route to and from site – A12 and B1122 East.
RETURN TO SEARCHBe the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!