Activity: Wide Load
Start date: 18th January 2025
End date: 25th January 2025
Updated 21 January.
On Tuesday 21 January, there are two wide load movements planned.
These loads will be delivering welfare units to Trust Farm. These loads are expected to arrive at 13:00 pm. These will be police escorted
On Thursday 23 January, there are six wide load movements planned.
The first two loads will be the removal of an excavator and dumper truck from Trust Farm. These loads are expected to depart at 10:00 am. These will be police escorted.
These loads will follow the designated route to and from site- B1122 West and A12.
The remaining four loads will be the removal of water tanks from the Temporary Construction Area. These loads are expected to leave at 10:00 am and 14:00 pm. These will be police escorted.
These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.
On Friday 24 January, there are five wide load movements planned.
There will be three loads that will be the removal of water tanks from the Temporary Construction Area. The first two loads are expected to leave at 09:00 am with the third load at 13:00pm. These will be police escorted.
These loads will follow the designated route to and from site – Lovers Lane, B1122 West and A12.
The remaining two loads include the removal of a plant from the Main Construction Site at 09:00am and a delivery of an excavator to the main development site at 14:00 pm. These will be police escorted.
These loads will follow the designated route to and from site.