Activity: Wide Load

Start date: 19th April 2024

End date: 27th April 2024

AIL movements in relation to the Sizewell C Project.

Updated 24 April 2024

Week commencing 22 April 2024.

On Monday 22 April we have 2 wide load movements that will be police escorted. Both deliveries will be travelling to the Ancillary Construction Area. The first delivery is expected to arrive at 11am delivering a Caterpillar bulldozer. The second delivery is expected to arrive at 12 noon, delivering a dumper truck to the site.

These loads will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.

On Wednesday 24 April we have 2 wide load movements that will be police escorted. Both deliveries will be travelling to the Temporary Construction Area and are expected to arrive on site at 12 noon delivering articulated dump trucks.

These loads will follow the designated route to and from site – A12, B1122 east and Lovers Lane.

On Thursday 25 April we have four wide load movements that will be police escorted.

The first two loads are expected to arrive at 11:00 am and the next two loads are expected to arrive at 13:00 pm, delivering welfare units to the Ancillary Construction Site.

These loads will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.

On Friday 26 April we have nine wide load movements that will be police escorted.

The first delivery is expected to arrive at 10am, delivering an excavator to the Temporary Construction Area.

This load will follow the designated route to and from site – A12, B1122 east and Lovers Lane.

The second delivery is expected to arrive at 11 am, delivering an excavator to the Ancillary Construction Area.

This load will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.

The third delivery is expected to arrive at the Main Construction Area at 12 noon, delivering an excavator.

This load will follow the designated route to and from site – A12, B1122 east and, Lovers Lane and Sizewell Gap Road.

The fourth and fifth delivery is expected to arrive at 10 am, delivering cabins to the Ancillary Construction Area.

These loads will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.

The sixth and seventh  delivery is expected to arrive at 11 am, delivering cabins to the Ancillary Construction Area.

These loads will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.

The eighth and ninth delivery is expected to arrive at 12 noon, delivering cabins to the Ancillary Construction Area.

These loads will follow the designated route to and from site – A12, B1122 east, Lovers Lane and King George’s Avenue.