Main Development Site

Activity: Wide Load

Start date: 28th June 2024

End date: 6th July 2024

AIL movements in relation to the Sizewell C Project.

Updated 3 July.

On Monday 1 July, there is one wide load movements, planned. This will be a delivery of an Articulated Dump Truck to the Ancillary Construction Area. This load is expected to arrive at 11:00 am. This will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East, Lovers Lane and King George Avenue.

On Tuesday 2 July, there will be two wide load movements, planned.

Both will be a delivery of an excavators to the Temporary Construction Area. These loads are expected to arrive at 12:00 noon. This will be police escorted.

These loads will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Wednesday 3 July, there is one wide load movements, planned. This will be a delivery of an articulated dump truck to the Temporary Construction Area. This load is expected to arrive at 09:00 am. This will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Friday 5 July, there are five wide load movements, planned.

The first and second movement will be the delivery of two articulated dump trucks to the Temporary Construction Area.  These loads are expected to arrive at 12:00 noon and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The third movement will be the transfer of an articulated dump truck from the Temporary Construction Area to the Main Construction Area. This load is expected to arrive at 13:00 pm and will be police escorted.

This load will follow the designated route to and from site – Lovers Lane and Sizewell Gap Road.

The fourth movement will be the removal of an articulated dump truck from the Temporary Construction Area and will be taken away from site. This is expected to leave at 13:00 pm and will be police escorted.

This load will follow the designated route to and from site – Lovers Labe B1122 West and the A12.

The fifth movement will be the transfer of an articulated dump truck from the Temporary Construction Area to the Main Construction Area. This load is expected to arrive at 15:00 pm and will be police escorted.

This load will follow the designated route to and from site – Lovers Lane and Sizewell Gap Road.