back
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 21st June 2024

End date: 30th June 2024

AIL movements in relation to the Sizewell C Project.

Updated 24 June.

Week commencing 24 June 2024.

On Monday 24 June, there are four wide load movements planned.

The first movement will be delivering an excavator to the Temporary Construction Area. This load is expected to arrive at 11:00am. These will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The second movement will be delivering an excavator to the Temporary Construction Area. This load is expected to arrive at 12:00 noon. These will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The third movement will be relocating an articulated dump truck to Main Construction Area from the Ancillary Construction Site. This load is expected to arrive at 12:00 noon. These will be police escorted.

This load will follow the designated route to and from site – King George Avenue and Sizewell Gap Road.

The fourth movement will be delivering an articulated dump truck to the Temporary Construction Area. This load is expected to arrive at 13:00 PM. These will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

On Tuesday 25 June there is one wide load movement planned. A delivery of an excavator will be travelling to the Temporary Construction Site and is expected to arrive at 11:00 am. This will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.