Activity: Wide Load
Start date: 27th July 2024
End date: 3rd August 2024
Updated 1 August 2024.
On Friday 2 August, there are two wide load movements planned.
The first load will be delivering a plant to the Temporary Construction Area. This load is expected to arrive at 10:00 am and will be police escorted.
This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.
The second load will be a delivery of an excavator to the Temporary Construction Area to be taken away from site. This load will be expected to arrive at 14:00 and will be police escorted.
This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.