back
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

Activity: Wide Load

Start date: 27th July 2024

End date: 3rd August 2024

AIL movements in relation to the Sizewell C Project.

Updated 1 August 2024.

On Friday 2 August, there are two wide load movements planned.

The first load will be delivering a plant to the Temporary Construction Area. This load is expected to arrive at 10:00 am and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.

The second load will be a delivery of an excavator to the Temporary Construction Area to be taken away from site. This load will be expected to arrive at 14:00 and will be police escorted.

This load will follow the designated route to and from site – A12, B1122 East and Lovers Lane.