Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 1st March 2025
  • End Date: 7th February 2025

Updated 6 March

On Monday 3 March, there are seven wide load movements planned.

At 12:00 there will a delivery of four cabins to the Green Rail Route compound.

At 13:00 there will a delivery of three cabins to the Green Rail Route compound.

 

On Tuesday 4 March, there are elven wide load movements planned.

At 11:00 there will a delivery of four two modular buildings to the Temporary Construction Area.

At 12:00 there will a delivery of two cabins to the Green Rail Route compound.

At 13:00 there will a delivery of one cabin to the Green Rail Route compound and two deliveries of building materials to the Temporary Construction Area.

At 14:00 there will be a delivery of two modular buildings to the Temporary Construction Area.

At 15:00 there will be a delivery of two modular buildings to the Temporary Construction Area.

 

On Wednesday 5 March, there are ten wide load movements planned.

At 11:00 there will  be a delivery of two modular buildings to the Temporary Construction Area.

At 12:00 there will be a delivery of two modular buildings to the Temporary Construction Area.

At 13:00 there will be two deliveries of building materials to the Temporary Construction Area.

At 14:00 there will be a delivery of two modular buildings to the Temporary Construction Area.

At 15:00 there will be two deliveries of building materials to the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.

 

On Thursday 6 March, there are 12 wide load movements planned:

At 11:00 there will be three deliveries to the Main Construction Area, these include an excavator, dozer and a mobile crane.

At 11:00 there will be three deliveries to the Temporary Construction Area of a mobile crane and two modular buildings.

At 13:00 two modular buildings will be delivered to the Temporary Construction Area.

At 14:00 two modular buildings will be delivered to the Temporary Construction Area.

At 15:00 two modular buildings will be delivered to the Temporary Construction Area.

On Friday 7 March, there are eight wide load movements planned.

At 09:00 there will a delivery of an excavator to the Main Development Site.

At 11:00 there will a delivery of two modular buildings to the Temporary Construction Area.

At 12:00 there will a two deliveries of building materials to the Temporary Construction Area.

At 14:00 there will be a delivery of two modular buildings to the Temporary Construction Area and a removal from site of a modular building.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.