Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 5th April 2025
  • End Date: 11th April 2025

On Monday 7 April, there are two wide load movements planned.

At 11:00 two excavators are being delivered to the Temporary Construction Area.

On Tuesday 8 April, there are three wide load movements planned.

At 11:00 three excavators are being delivered to the Temporary Construction Area.

On Wednesday 9 April, there is one wide load movement planned.

At 11:00 one excavator is being delivered to the Temporary Construction Area.

On Thursday 10 April, there are two wide load movements planned.

At 09:00 a bulldozer is being delivered to the Temporary Construction Area.

At 11:00 an excavator is being delivered to the Temporary Construction Area.

At 14:00 two excavators are being delivered to the Ancillary Construction Area.

On Friday 10 April, there is one wide load movement planned.

At 12:00 a storage container is delivered to the Main Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.