On Monday 7 April, there are two wide load movements planned.
At 11:00 two excavators are being delivered to the Temporary Construction Area.
On Tuesday 8 April, there are three wide load movements planned.
At 11:00 three excavators are being delivered to the Temporary Construction Area.
On Wednesday 9 April, there is one wide load movement planned.
At 11:00 one excavator is being delivered to the Temporary Construction Area.
On Thursday 10 April, there are two wide load movements planned.
At 09:00 a bulldozer is being delivered to the Temporary Construction Area.
At 11:00 an excavator is being delivered to the Temporary Construction Area.
At 14:00 two excavators are being delivered to the Ancillary Construction Area.
On Friday 10 April, there is one wide load movement planned.
At 12:00 a storage container is delivered to the Main Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.
RETURN TO SEARCHBe the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!