On Wednesday 7 May, there are eleven wide load movements planned.
At 09:00, the removal of a plant machinery will take place from the Main Construction Area.
At 10:00, there will be a delivery of a dumper truck to the Ancillary Construction Area.
At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.
At 12:00, there will be a removal of a dumper truck from the Ancillary Construction Area and two excavators being delivered to the Main Construction Area.
At 14:00, there will be a delivery of an excavator and a removal of an excavator at the Main Construction Area.
At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.
On Thursday 8 May, there are eight wide load movements planned.
At 09:00, the removal of two dumper trucks from the Temporary Construction Area.
At 10:00, there will be a delivery of a dumper truck to the Ancillary Construction Area.
At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.
At 14:00, there will be a delivery of two dumper truck to the Temporary Construction Area.
At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.
On Friday 9 May, there are four wide load movements planned.
At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.
At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.
RETURN TO SEARCH
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!