Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 2nd May 2025
  • End Date: 9th May 2025

On Wednesday 7 May, there are eleven wide load movements planned.

At 09:00, the removal of a plant machinery will take place from the Main Construction Area.

At 10:00, there will be a delivery of a dumper truck to the Ancillary Construction Area.

At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.

At 12:00, there will be a removal of a dumper truck from the Ancillary Construction Area and two excavators being delivered to the Main Construction Area.

At 14:00, there will be a delivery of an excavator and a removal of an excavator at the Main Construction Area.

At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.

On Thursday 8 May, there are eight wide load movements planned.

At 09:00, the removal of two dumper trucks from the Temporary Construction Area.

At 10:00, there will be a delivery of a dumper truck to the Ancillary Construction Area.

At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.

At 14:00, there will be a delivery of two dumper truck to the Temporary Construction Area.

At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.

On Friday 9 May, there are four wide load movements planned.

At 11:00, there will be two deliveries of sheet piles to the Main Construction Area.

At 15:00, there will be two deliveries of sheet piles to the Main Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 East & Lovers Lane.

 