Updated 10 July.
On Monday 8 July, there are two wide load movements planned.
The first will be the transfer of a modular office from the Ancillary Construction Area to the Main Development Site. This load is expected to arrive at 09:00 am and will be police escorted.
This load will follow the designated route to and from site – King George Ave and Sizewell Gap Road.
The second movement will be the transfer of an articulated dump truck from the Sports & Social club to the Main Construction Area. This load is expected to arrive at 12:00 noon and will be police escorted.
This load will follow the designated route to and from site – King George Avenue and Sizewell Gap Road.
On Tuesday 9 July, there is one wide load movements planned. This will be a collection of an excavator from the Ancillary Construction Area and will be transported away from the area. This load is expected to leave at 10:00 am and will be police escorted.
This load will follow the designated route to and from site – King George Ave, Lovers Lane, B1122 West & A12.
On Thursday 11 July, there is one wide load movements planned. This will be a collection of an excavator from the Temporary Construction Area and will be transported away from the area. This load is expected to leave at 14:00 am and will be police escorted.
This load will follow the designated route to and from site, Lovers Lane, B1122 West & A12.
RETURN TO SEARCH
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!