Activity: Archaeology
Start date: 16th August 2024
End date: 31st December 2024
Sizewell C will begin preparation works to enable the archaeology works to commence in the vicinity of Middleton Road in preparation for the construction the roundabout.
In order to create a safe working environment at the location, we will create a bell-mouth entrance and a welfare compound for our workers to conduct archaeological works. The compound will consist of car parking, portacabin style facilities and safe walk ways.
These works are due to commence on 10 September 2024 and will take approximately 2 weeks.
Archaeology works will then commence the week of 9 October 2024.