Destinations:
MCA - Main Construction Area
ACA - Ancillary Construction Area
TCA - Temporary Construction Area
GRR - Green Rail Route Compound
SLR - Sizewell Link Road
| Start Date & Time | Load Description | Gate | Delivery/Collection | Route |
| 12/10/2026 10:00 | 1 x Load(s) of plant | Plaza Roundabout | Collection | Route 1a A12 Sevenhills to Plaza Roundabout |
| 12/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 12/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 12/10/2026 11:00 | 1 x Load(s) of collection of 25t excavator | TCA | Collection | Route 2a Lowestoft to Plaza Roundabout |
| 12/10/2026 14:00 | 1 x Load(s) of collection of 20T excavator | TCA | Collection | Route 1a A12 Seven Hills to TCA |
| 13/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 13/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 14/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 14/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 15/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 15/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 16/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
| 16/10/2026 11:00 | 1 x Load(s) of STORAGE TANK | TCA | Delivery | Route 2a Lowestoft to TCA |
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!