On Monday 22 September, there are ten wide load movement currently planned:
At 09:00, two modular buildings will be delivered to the Main Construction Area. An excavator will be collected and removed from the Temporary Construction Area.
At 11:00, two modular buildings will be delivered to the Main Construction Area.
At 13:00, two modular buildings will be delivered to the Main Construction Area.
At 15:00, two modular buildings and plant machinery will be delivered to the Main Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!