Wide & Abnormal Load movements w/c 26 October 2026

By SZC Community Relations | Published on 23rd October 2026

AIL movements in relation to the Sizewell C Project

Destinations:

MCA/MDS - Main Construction Area

ACA - Ancillary Construction Area

TCA - Temporary Construction Area

GRR - Green Rail Route Compound

SLR - Sizewell Link Road

Start Date & Time Load Description Gate Delivery/Collection Route
26/10/2026 09:00 Crane TCA Delivery Designated Route A12, B1122 & Lovers Lane
26/10/2026 09:00 Concrete Pump TCA Delivery Designated Route A12, B1122 & Lovers Lane
26/10/2026 10:00 Excavator TCA Delivery Designated Route A12, B1122 & Lovers Lane
26/10/2026 10:00 Road Rail Vehicle Green Rail Route Buckleswood Delivery Designated Route A12, B1122 & Lovers Lane
28/10/2026 09:00 Plant Machinary TCA TransitOnly Designated Route A12, B1122 & Lovers Lane
28/10/2026 09:00 Crane TCA Delivery Designated Route A12, B1122 & Lovers Lane
28/10/2026 09:00 Crane TCA Delivery Designated Route A12, B1122 & Lovers Lane
28/10/2026 15:00 Crane TCA DepartureOnly Designated Route A12, B1122 & Lovers Lane
29/10/2026 15:00 Plant Machinary TCA DepartureOnly Designated Route A12, B1122 & Lovers Lane
30/10/2026 14:00 Crane TCA Collection Designated Route A12, B1122 & Lovers Lane
30/10/2026 15:00 Crane TCA Departure Only Designated Route A12, B1122 & Lovers Lane