On Monday 27 October there are four wide load movements planned.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
On Tuesday 28 October there are twelve wide load movements planned.
At 09:00, a crane is being collected and taken away from the Main Construction Site.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
At 12:00, two deliveries of materials will be made to the Main Construction Site.
At 14:00, an articulated dump truck is being removed from the Temporary Construction Area.
At 15:00, two cranes, two plant machines and a load of sheet piles will be delivered to the Temporary Construction Area.
On Wednesday 29 October there are eleven wide load movements planned.
At 09:00, a crane will be removed from the Main Construction Site.
At 10:00, an excavator will be removed from the Main Construction Site.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area, and a dumper truck and excavator will be delivered to Trust Farm compound.
At 13:00, a delivery of materials will be made to the Temporary Construction Area.
At 14:00, a bulldozer will be delivered to Trust Farm compound.
At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area, and a dumper truck will be delivered to the Trust Farm compound.
On Thursday 30 October there are six wide load movements planned.
At 09:00, two deliveries of rail panels will be made to the Temporary Construction Area.
At 10:00, an excavator will be delivered to the Main Construction Area, and an excavator will be removed from the compound on Buckleswood Road.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!