Wide & Abnormal Load movements w/c 28 September 2026

By SZC Community Relations | Published on 25th September 2026

AIL movements in relation to the Sizewell C Project

Destinations:

MCA - Main Construction Area

ACA - Ancillary Construction Area

TCA - Temporary Construction Area

GRR - Green Rail Route Compound

SLR - Sizewell Link Road

Start Date & Time Load Description Gate Delivery/Collection Route
28/09/2026 09:00 Concrete Pump TCA Delivery Designated Route A12, B1122 & Lovers Lane
28/09/2026 09:00 Excavator TCA Collection Designated Route A12, B1122 & Lovers Lane
28/09/2026 11:00 Batching Cabin Trailer TCA Delivery Designated Route A12, B1122 & Lovers Lane
29/09/2026 09:00 Concrete Pump TCA Delivery Designated Route A12, B1122 & Lovers Lane
29/09/2026 11:00 Silo MCA Delivery Designated Route A12, B1122 & Lovers Lane
29/09/2026 11:00 Silo MCA Delivery Designated Route A12, B1122 & Lovers Lane
29/09/2026 13:00 Plant Machinery TCA Delivery Designated Route A12, B1122 & Lovers Lane
29/09/2026 15:00 Bull Dozer TCA Delivery Designated Route A12, B1122 & Lovers Lane
30/09/2026 11:00 Crane Green Rail Route Buckleswood Collection Designated Route A12, B1122 & Lovers Lane
30/09/2026 11:00 Excavator OSI 380 Pretty Road Collection Designated Route A12, B1122 & Lovers Lane
01/10/2026 09:00 Concrete Pump TCA Delivery Designated Route A12, B1122 & Lovers Lane
01/10/2026 11:00 Storage Tank TCA Delivery Designated Route A12, B1122 & Lovers Lane
01/10/2026 11:00 Storage Tank TCA Delivery Designated Route A12, B1122 & Lovers Lane
02/10/2026 09:00 Concrete Pump TCA Delivery Designated Route A12, B1122 & Lovers Lane
02/10/2026 11:00 Storage Tank TCA Delivery Designated Route A12, B1122 & Lovers Lane
02/10/2026 11:00 Storage Tank TCA Delivery Designated Route A12, B1122 & Lovers Lane

Subscribe for Sizewell C Activity Alerts