Site construction
Leiston-cum-Sizewell

Main Development Site

  • Activity: Site construction
  • Start Date: 24th July 2026
  • End Date: 2nd April 2027

The works to install the sheet pile wall for the temporary sea defence have now been completed. From September, work is expected to begin to install rock armour around the southern end of the sea defence.

To allow the rock armour to be installed safely, a slight temporary realignment of the coastal footpath has been implemented.

Once the rock armour has been installed, the footpath will be returned to its current position.

The rock armour installation is expected to be completed early in 2027.

Thank you for your patience and understanding while these important sea defence works continue.