Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 11th July 2025
  • End Date: 18th July 2025

On Monday 14 July, there are seven wide load movements currently planned:

At 09:00, there will be a delivery and a collection of a bulldozer from the Main Construction Site.

At 10:00, a plant machinery is being delivered to Temporary Construction Area.

At 11:00, two deliveries of sheet piles are being made to the Main Construction Site.

At 15:00, two deliveries of sheet piles are being to the Main Construction Area.

On Wednesday 16 July, there are nine wide load movements currently planned:

At 10:00, there will be a delivery of a piling rig to the Main Construction Site.

At 11:00, two deliveries of sheet piles are being made to the Main Construction Site.

At 12:00, two cabins are being delivered to Ancillary Construction Area.

At 13:00, two cabins are being delivered to Ancillary Construction Area.

At 15:00, two deliveries of sheet piles are being made to the Main Construction Site.

On Thursday 17 July, there are six wide load movements currently planned:

At 09:00, two bulldozers are being relocated from the Main Construction Site to Pretty Road compound. Additionally, a crane is being delivered to the Main Construction Site.

At 10:00, a delivery of plant machinery is being made to the Main Construction Site.

At 14:00, an excavator is being delivered to the Main Construction Site.

At 15:00, ta crane is being delivered to the Main Construction Site.

On Friday 18 July, there is one wide load movements currently planned:

At 14:00, a bulldozer is being delivered to the Main Construction Site.

All the above movements will be police escorted and will follow the designated route to site via the A12, B1122 East & Lovers Lane.