Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 25th July 2025
  • End Date: 1st August 2025

 

On Wednesday30 July, there are two wide load movement currently planned:

At 09:00, a plant equipment will be leaving the Temporary Construction Area.

At 13:00, a dumper truck will be leaving the Main Construction Site.

On Thursday31 July, there are four wide load movement currently planned:

At 10:00, two deliveries of welfare units to the Temporary Construction Area.

At 11:00, two deliveries of welfare units to the Temporary Construction Area.

On Friday 1 August, there are two wide load movement currently planned:

At 11:00, an dumper truck is being delivered to the Temporary Construction Area.

At 15:00, a delivery of plant machinery  to the Main Construction Area.

All the above movements will be police escorted and will follow the designated route to site via the A12, B1122 East & Lovers Lane.

RETURN TO SEARCH

Subscribe for Sizewell C Activity Alerts

SUBSCRIBE FOR ALERTS