From 16 February, Sizewell C will commence the construction of the Marine Bulk Import Facility (MBIF) which will require a temporary partial closure of the footpath in the immediate area.
The MBIF will extend approximately 500 metres from the Main Construction Site into the North Sea, supporting our strategy to deliver 60% of construction materials by rail and sea.
To construct the facility, we will be using a cantitravel system to install piles that will support the platform. This platform will enable the movement of materials from import vessels directly to the site.
Public Safety and Footpath Access
To ensure public safety during construction, Sizewell has submitted a request to temporarily close the coastal footpath in the vicinity of the works.
The footpath will remain open at weekends and be closed during the week
The footpath will fully reopen once construction progresses into the North Sea. We anticipate this work will be complete by the end of March 2026 and will keep you informed of progress.
A longer in-land diversionary route will be available during the closure period and this can be viewed here: MBIF_Alt_Route_NOV25_V6
RETURN TO SEARCH
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!