Site construction
Leiston, Leiston-cum-Sizewell

Wild Studio

  • Activity: Site construction
  • Start Date: 3rd February 2025
  • End Date: 31st December 2026

Works are underway to create a water management zone  if the field adjacent to Wild Studio and Sandy Lane.

Archaeology work in studio field is currently underway.

Once the archaeology work is complete we will install the pipe work along studio field to connect to the water management facility which will be constructed and a temporary haul road will be constructed to support the construction of the facility.