Site construction
Kelsale cum Carlton

Sizewell Link Road

  • Activity: Site construction
  • Start Date: 3rd August 2026
  • End Date: 16th August 2026

Works are about to start on the construction of the foundations of the new bridge over the railway as part of the Sizewell Link Road.

The bridge is an important part of the bypass and will allow the new road to cross over the railway line. Before the bridge structure can be built, we need to install piles into the ground. These piles will create the foundations needed to safely support the bridge.

What work will be taking place?

  • Piling platform works on both sides of the railway boundary, to create safe working areas for the piling rig.
  • Installation of ground improvement piles and bridge foundation piles.
  • Use of construction plant, including piling rigs, cranes, excavators, rollers and delivery vehicles.
  • Movement of materials through the site using the established haul routes and temporary access arrangements.

Due to the nature of these works, some noise will be unavoidable. We will work to keep disruption to a minimum wherever possible.