TRAFFIC MANAGEMENT TRAFFIC MANAGEMENT Sizewell C related Traffic Management, Road Closures & Rail Movements Published: 13th November 2026

Please see below for current and up and coming train movements, road closures and traffic management in relation to the Sizewell C project: Engineering Train Movements  Train Movements Monday Tuesday Wednesday Thursday Friday Saturday Sunday Train 1 Inbound Pass Ipswich […]

Learn more
WIDE LOAD WIDE LOAD Wide & Abnormal Load movements w/c 16 November 2026 Published: 13th November 2026

AIL movements in relation to the Sizewell C Project Destinations: MCA/MDS – Main Construction Area ACA – Ancillary Construction Area TCA – Temporary Construction Area GRR – Green Rail Route Compound SLR – Sizewell Link Road Start Date & Time […]

Learn more
GENERAL ACTIVITY GENERAL ACTIVITY Project Update – October 2026 Published: 6th November 2026

Introduction As we head into the autumn and winter months, Sizewell C is working closely with other infrastructure and energy projects in the area as we navigate required road closures.  We are working closely with Essex and Suffolk Water as […]

Learn more
TRAFFIC MANAGEMENT TRAFFIC MANAGEMENT Sizewell C related Traffic Management, Road Closures & Rail Movements Published: 6th November 2026

Please see below for current and up and coming train movements, road closures and traffic management in relation to the Sizewell C project: Engineering Train Movements  Train Movements Monday Tuesday Wednesday Thursday Friday Saturday Sunday Train 1 Inbound Pass Ipswich […]

Learn more
WIDE LOAD WIDE LOAD Wide & Abnormal Load movements w/c 9 November 2026 Published: 6th November 2026

AIL movements in relation to the Sizewell C Project Destinations: MCA/MDS – Main Construction Area ACA – Ancillary Construction Area TCA – Temporary Construction Area GRR – Green Rail Route Compound SLR – Sizewell Link Road Start Date & Time […]

Learn more
MARINE MARINE Marine Activity Update Published: 14th April 2026

On or about the 16th of April 2026, works will commence to pull in the pipe to line the Combined Drainage Outfall (CDO). These works are complex and will involve several vessels and the jack-up barge NP497. Diving operations will […]