As part of the construction phase of Sizewell C nuclear power station, footpath Leiston-cum-Sizewell 3 Public Rights of Way (PRoW) will be diverted 10 metres to the west for a length of 40 metres, north of the Hodgson Avenue pedestrian crossing of the Saxmundham to Leiston railway. This is to allow the construction of the Green Rail Route.
The diversion will be in place from the 7 November 2025 to the 30 June 2026. On the 13 and 14 November 2025 the path will be closed to facilitate track laying.
RETURN TO SEARCHBe the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!