Site construction
Leiston-cum-Sizewell, Saxmundham, Theberton and Eastbridge

Land East of Eastlands Industrial Estate (LEEIE)

  • Activity: Site construction
  • Start Date: 15th September 2025
  • End Date: 9th January 2026

Works on constructing the sidings at the ACA will begin the week of the 22 September with the installation of the bottom ballast. This will involve wackers, dumpers and cranes to move and compact the ballast.

This will take approx. 2 weeks.

Once the bottom ballast has been installed work will begin on installing the track.