Site construction
Marlesford

Southern Park and Ride

  • Activity: Site construction
  • Start Date: 15th September 2025
  • End Date: 14th November 2025

UKPN are  installing a power line to the Park & Ride site that will run from a connection point on the A12 (outside the Farm Shop at Marlesford) the works will commence from 15 September until the 9 November. The works will, at times, require traffic Management (lights) along A12 from the Farm Shop and a lane closure. Marlesford Road will also have to be temporarily closed whilst cable is laid.  

 