Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 14th November 2025
  • End Date: 21st November 2025

On Monday 17 November there are  two  wide load movements planned:

At 11:00, plant machinery will be removed from the Main Construction Site.

At 15:00, a storage tank will be delivered to the Main Construction Site.

On Tuesday 18 November there are eleven wide load movements planned.

At 09:00, three deliveries of construction materials will be made to the Green Rail Route Compound.

At 10:00, a delivery of construction materials will be made to the Main Construction Site.

At 11:00, two dumper trucks will be delivered to the Temporary Construction Area.

At 12:00, a delivery of a crane will be made to the Temporary Construction Area and two dumper trucks will be taken away from site. A delivery of materials will also be made to the Green Rail Route compound.

At 14:00, a crane will be delivered to the Temporary Construction Area.

On Wednesday 19 November there are nine wide load movements planned.

At 09:00, two portable offices will be delivered to the Main Construction Site and three deliveries of materials to the Green Rail Route compound.

At 12:00, a delivery of materials will be made to the Green Rail Route compound.

At 13:00. A delivery of steel pipes will be made to the Main Construction Are and two excavators will be removed from the Temporary Construction Area.

On Wednesday 19 November there are nine wide load movements planned.

At 09:00, two portable offices will be delivered to the Main Construction Site and three deliveries of materials to the Green Rail Route compound.

At 12:00, a delivery of materials will be made to the Green Rail Route compound.

At 13:00. A delivery of steel pipes will be made to the Main Construction Are and two excavators will be removed from the Temporary Construction Area.

On Friday 21 November there are three wide load movements planned.

At 09:00, two excavators will be removed from the Temporary Construction Area.

At 11:00, a dumper truck delivered to the Temporary Construction Area.

At 12:00, a dumper truck will be removed from the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane