Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 24th October 2025
  • End Date: 31st October 2025

On Monday 27 October there are four wide load movements planned.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

On Tuesday 28 October there are twelve wide load movements planned.

At 09:00, a crane is being collected and taken away from the Main Construction Site.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

At 12:00, two deliveries of materials will be made to the Main Construction Site.

At 14:00, an articulated dump truck is being removed from the Temporary Construction Area.

At 15:00, two cranes, two plant machines and a load of sheet piles will be delivered to the Temporary Construction Area.

On Wednesday 29 October there are eleven wide load movements planned.

At 09:00, a crane will be removed from the Main Construction Site.

At 10:00, an excavator will be removed from the Main Construction Site.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area, and a dumper truck and excavator will be delivered to Trust Farm compound.

At 13:00, a delivery of materials will be made to the Temporary Construction Area.

At 14:00, a bulldozer will be delivered to Trust Farm compound.

At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area, and a dumper truck will be delivered to the Trust Farm compound.

On Thursday 30 October there are six wide load movements planned.

At 09:00, two deliveries of rail panels will be made to the Temporary Construction Area.

At 10:00, an excavator will be delivered to the Main Construction Area, and an excavator will be removed from the compound on Buckleswood Road.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.