Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 8th August 2025
  • End Date: 15th August 2025

On Monday 11 August, there are four wide load movement currently planned:

At 10:00, a crane will be delivered to the Main Construction Site.

At 11:00, a delivery of sheet piles will arrive at the Temporary Construction Area.

At 12:00, a delivery of sheet piles will arrive at the Temporary Construction Area.

At 15:00, a delivery of sheet piles will arrive at the Main Construction Site.

On Tuesday 12 August, there are fifteen wide load movement currently planned:

At 10:00, a crane will be delivered to the Main Construction Site.

At 11:00, a delivery of sheet piles and two modular buildings will arrive at the Temporary Construction Area. A further deliver of plant machinery parts is being made to the Main Development Site.

At 12:00, a delivery of sheet piles and two modular buildings will arrive at the Temporary Construction Area. A further deliver of plant machinery parts is being made to the Main Development Site.

At 13:00, two modular buildings will be delivered to the Temporary Construction Area.

At 14:00, two modular buildings will be delivered to the Temporary Construction Area.

At 15:00, two deliveries of sheet piles will be made to the Main Construction Site.

On Wednesday 13 August, there are four wide load movement currently planned:

At 11:00, a modular building and one load of sheet piles is being delivered to the Temporary Construction Area. Two excavators are being delivered to the plaza roundabout compound.

On Friday 15 August, there are nine wide load movement currently planned:

At 11:00, a crane will be leaving the Temporary Construction Area and taken away from site. There will also be two modular buildings being delivered to the Temporary Construction Area.

At 12:00, two modular buildings are being delivered to the Temporary Construction Area.

At 13:00, two modular buildings are  being delivered to the Temporary Construction Area.

At 14:00, two modular buildings will be delivered to the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site via the A12, B1122 East & Lovers Lane.