On Monday 6 October, there are eight wide load movements currently planned:
At 10:00am, a crane will be delivered to the Main Construction Area.
At 11:00, two storage tanks will be delivered to the Main Construction Site. At the same time two loads of sheet piles will be made to the Temporary Construction Area.
At 14:00, a dumper truck will be delivered to our compound at Trust Farm.
At 15:00, two loads of sheet piles will be delivered to the Temporary Construction Area.
On Tuesday 7 October, there are eight wide load movements currently planned:
At 09:00am, an excavator will be delivered to our compound the Temporary Construction Area.
At 11:00, two storage tanks will be delivered to the Main Construction Site. At the same time two loads of sheet piles will be made to the Temporary Construction Area.
At 14:00, a dumper truck will be delivered to our compound at Trust Farm.
At 15:00, two loads of sheet piles will be delivered to the Temporary Construction Area.
On Wednesday 8 October, there are nine wide load movements currently planned:
At 11:00, an excavator will be delivered to the Main Construction Area. Two deliveries of sheet piles will be made to the Temporary Construction Area. At the same time, a rig will be collected and removed from the Temporary Construction Area.
At 12:00, an excavator will be delivered to the Main Construction Area.
At 13:00, two excavators will be delivered to the Temporary Construction Area.
At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
On Thursday 7 October, there are eleven wide load movements currently planned:
At 09:00, two modular buildings will be delivered to the Main Construction Site. Two bulldozers will be removed from the Temporary Construction Area.
At 10:00, an excavator will be made to the Temporary Construction Area.
At 11:00, a rig will be delivered to the Main Construction Site. At the same time, two deliveries of sheet piles will be made to the Temporary Construction Area.
At 12:00, two excavators will be delivered the Ancillary Construction Area.
At 15:00, a delivery of sheet piles will be made to the Temporary Construction Area.
On Friday 10 October there are five wide load movements planned.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
At 13:00, an excavator will be delivered to our rail compound at Buckleswood Road.
At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.
RETURN TO SEARCHBe the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!