Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 3rd October 2025
  • End Date: 10th October 2025

On Monday 6 October, there are eight wide load movements currently planned:

At 10:00am, a crane will be delivered to the Main Construction Area.

At 11:00, two storage tanks will be delivered to the Main Construction Site. At the same time two loads of sheet piles will be made to the Temporary Construction Area.

At 14:00, a dumper truck will be delivered to our compound at Trust Farm.

At 15:00, two loads of sheet piles will be delivered to the Temporary Construction Area.

On Tuesday 7 October, there are eight wide load movements currently planned:

At 09:00am, an excavator will be delivered to our compound the Temporary Construction Area.

At 11:00, two storage tanks will be delivered to the Main Construction Site. At the same time two loads of sheet piles will be made to the Temporary Construction Area.

At 14:00, a dumper truck will be delivered to our compound at Trust Farm.

At 15:00, two loads of sheet piles will be delivered to the Temporary Construction Area.

On Wednesday 8 October, there are nine wide load movements currently planned:

At 11:00, an excavator will be delivered to the Main Construction Area. Two deliveries of sheet piles will be made to the Temporary Construction Area. At the same time, a rig will be collected and removed from the Temporary Construction Area.

At 12:00, an excavator will be delivered to the Main Construction Area.

At 13:00, two excavators will be delivered to the Temporary Construction Area.

At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

On Thursday 7 October, there are eleven wide load movements currently planned:

At 09:00, two modular buildings will be delivered to the Main Construction Site. Two bulldozers will be removed from the Temporary Construction Area.

At 10:00, an excavator will be made to the Temporary Construction Area.

At 11:00, a rig will be delivered to the Main Construction Site. At the same time, two deliveries of sheet piles will be made to the Temporary Construction Area.

At 12:00, two excavators will be delivered the Ancillary Construction Area.

At 15:00, a delivery of sheet piles will be made to the Temporary Construction Area.

On Friday 10 October there are five wide load movements planned.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

At 13:00, an excavator will be delivered to our rail compound at Buckleswood Road.

At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area.

All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.