On Monday 8 September, there are six wide load movement currently planned:
At 09:00, a crane and crane matts will be delivered to the Main Construction Area.
At 11:00, two deliveries of sheet piles and an excavator are being delivered to the Main Construction Area.
At 15:00, two deliveries of sheet piles and an excavator are being delivered to the Main Construction Area.
On Tuesday 9 September, there are thirteen wide load movement currently planned:
At 09:00, a crane will be delivered to our compound adjacent to Lovers Lane. Two modular buildings will be delivered to the Main Construction Area.
At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area and two modular buildings are being delivered to the Main Construction Area.
At 13:00, two modular buildings are being delivered to the Main Construction Area.
At 13:00, two modular buildings are being delivered to the Main Construction Area.
At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area and two modular buildings are being delivered to the Main Construction Area.
On Wednesday 10 September, there are fourteen wide load movement currently planned:
At 09:00, two modular buildings will be delivered to the Main Construction Area.
At 11:00, two deliveries of sheet piles are being delivered to the Temporary Construction Area. Then two modular buildings, a crusher and plant machinery will be delivered to the Main Construction Area.
At 13:00, two modular buildings are being delivered to the Main Construction Area.
At 15:00, two modular buildings are being delivered to the Main Construction Area and two deliveries of sheet piles to the Temporary Construction Area.
On Thursday 11 September, there are sixteen wide load movement currently planned:
At 09:00, two modular buildings will be delivered to the Main Construction Area.
At 11:00, a welfare cabin is being moved from the Temporary Construction Area and two deliveries of sheet piles are being delivered to the Temporary Construction Area. Two further deliveries of modular buildings are being made to the Main Construction Area.
At 13:00, four modular buildings are being delivered to the Main Construction Area. Two welfare cabins are being removed from the Temporary Construction Area,
At 15:00, two deliveries of sheet piles are being made to the Temporary Construction Area.
All the above movements will be police escorted and will follow the designated route to site – A12, B1122 & Lovers Lane.
RETURN TO SEARCH
Be the first to know about key announcements and new information as it becomes available. Whether you're a local resident, stakeholder, or simply interested in the project, our updates will keep you in the loop and provide valuable insights directly to your inbox. Don't miss out. Register today and stay connected!