Wide load
Farnham with Stratford St Andrew, Hacheston, Leiston, Leiston-cum-Sizewell, Marlesford, Melton, Middleton cum Fordley, Theberton and Eastbridge, Woodbridge

Main Development Site

  • Activity: Wide load
  • Start Date: 5th September 2025
  • End Date: 12th September 2025

On Monday 8 September, there are six wide load movement currently planned:

At 09:00, a crane and crane matts will be delivered to the Main Construction Area.

At 11:00, two deliveries of sheet piles and an excavator are being delivered to the Main Construction Area.

At 15:00, two deliveries of sheet piles and an excavator are being delivered to the Main Construction Area.

On Tuesday 9 September, there are thirteen wide load movement currently planned:

At 09:00, a crane will be delivered to our compound adjacent to Lovers Lane. Two modular buildings will be delivered to the Main Construction Area.

At 11:00, two deliveries of sheet piles will be made to the Temporary Construction Area and two modular buildings are being delivered to the Main Construction Area.

At 13:00, two modular buildings are being delivered to the Main Construction Area.

At 13:00, two modular buildings are being delivered to the Main Construction Area.

buildings will be delivered to the Main Construction Area.

At 15:00, two deliveries of sheet piles will be made to the Temporary Construction Area and two modular buildings are being delivered to the Main Construction Area.

All the above movements will be police escorted and will follow the designated route to site via the A12, B1122 East & Lovers Lane.