AIL movements in relation to the Sizewell C Project. Updated 26 November 2024. On Monday 25 November, there are four wide load movements planned. The first two loads are delivering welfare units to the Ancillary Construction Area. These loads are expected to arrive at 13:00 pm. These will be police escorted. These loads will follow…
Sizewell C is currently surveying and clearing vegetation in the associated development areas of the Sizewell Link Road and Two Village Bypass. The Sizewell C ecology team are currently actioning vegetation clearance works across the sites of the associated developments. Sizewell C has worked with statutory bodies and specialists to assist with planning works to…
The following road closures are planned to facilitate collaborative working with several utility companies: Lovers Lane between the Junction of King George Avenue and Abbey Road. Period 30 October – 18 December 2024 Night time works only. Night time closures will run during the hours of 19:00 – 05:00. Residents living within the road…
AIL movements in relation to the Sizewell C Project. Updated 10 October 2024. On Monday 7 October, there is one abnormal load movement planned: This load will be an articulated dump truck departing the Temporary Construction Area at approximately 9am and will be police escorted. This load will follow the designated route from site –…